EV Charge San Diego (619) 202-8501 Get a free quote

EV charger permits in San Diego County, city by city

Each of the county's 18 cities runs its own permit office, and the County handles everywhere else. Find yours for where to apply, what to submit, how long it takes and how to book the inspection.

Checked against each office's own website on October 12, 2026.

Find your permit office

If your address is inside a city, that city issues the permit. Neighborhoods such as La Jolla and Pacific Beach go through the City of San Diego, and unincorporated communities such as Rancho Santa Fe and Fallbrook go through the County.

Permit office How to apply What a house submits Turnaround Inspection
Carlsbad Online, Customer Self Service portal (Residential PME permit) No plan set: checklist B-65A, circuit card B-36 and the charger specs Next business day after payment One inspection, booked online or at 442-339-2725
Chula Vista Accela Citizen Access, the city's online permitting platform None for a house, duplex or townhome Not published Citizen Access online, or the automated line at (619) 409-5434
Coronado Email, mail or in person (BUILDINGPERMITS@coronado.ca.us) The state's EV permitting checklist, unless the city adopts its own Administrative review; missing items listed in one written notice Call 619-522-7361 by 4 p.m. for the next business day
Del Mar Online through eTRAKiT (electrical permits) Not published for electrical-only work; exterior changes go to Planning first Not published 858-375-9528 or email by 4 p.m. for next-day service
El Cajon Online through PACO (Project Assistance Center Online) Scaled site plan; single-line diagram for a Level 2 charger at 50 A or more Not published As listed on your permit's inspection sheet
Encinitas Online only, Customer Self Service (CSS) portal Short digital plan set, stamped by a C-10 contractor or electrical engineer 1 to 3 business days (expedited goal) Booked in the CSS portal
Escondido Escondido Portal (trade permits); electronic plans only Site or floor plan, load calculation or single-line, maker's instructions Over the counter or within a day or two, if complete (2017 guideline) Through the Escondido Portal only
Imperial Beach Online, Citizen Self-Service (CSS) portal No home EV checklist published; circuit card and load summary at the panel Not published 619-628-1360, the CSS portal or email; Monday to Thursday
La Mesa MaintStar portal: Electrical, then EV Charger (EVCS) Title sheet and site plan, plus the city's EVCS checklist Expedited for qualified EVCS applications Online in MaintStar, 9 a.m. to 4 p.m.
Lemon Grove Online application page or the counter (Mon to Thu, 7:30 a.m. to noon) Ask the permit line; no checklist online Not published Leave a message at (619) 825-3808 before 3 p.m.
National City Plans by email as PDFs (10 MB limit) Site plan, load calculation, cut sheet and single-line (2015 bulletin) Not published Online, 24 hours ahead, Monday to Thursday
Oceanside Online permits through eTRAKiT; confirm with the city Not confirmed; ask the Building Division Not published Ask the Building Division
Poway Online Services (electronic submittals only) Ask the Building Division (858-668-4645) Not published 858-668-4646 or online, before 4 p.m. for the next business day
San Diego Online, as a Simple No Plan permit None for a single-family home, duplex or townhouse Not published $264.25 per charger; someone opens the panel for the inspector
San Marcos Online, permit type EVCS None for a house: eligibility checklist, EVSE guide and load worksheet 1 to 3 business days (single-family) Inspections page, or 760-744-1050 ext. 3260
Santee Santee Permitting and Licensing Portal Per the city's residential plug-in EV checklist Not published Requested through the city's inspection page
Solana Beach By email to Counter@cosb.org Site plan signed by a C-10 or engineer, load worksheet and specs Not published Required; scheduling not published online
Vista In person at the Development Services counter No single-family EV checklist published; ask the counter Not published 760-639-6106 or online, before 3:30 p.m. for the next business day
Unincorporated San Diego County Citizen Access Portal, record type 8013 Per the County's PDS 808 checklist Same day (instant permit) Booked in the Citizen Access Portal

Offices without a link don't publish enough about their EV process online for a step-by-step guide yet. Call them to confirm the details.

The steps every permit shares

The order is the same everywhere. What changes is the paperwork in step three and how each office books step six.

  1. Find your permit office

    Your city's building division, or the County for unincorporated areas. The table above lists all of them.

  2. Check the house can take it

    A load calculation shows whether the panel has room for the charger circuit, or whether you need a lower setting, a load-management device or a service upgrade.

  3. Put the application together

    The office's checklist, the charger's specifications and installation instructions, the load calculation, and a site plan where the office asks for one.

  4. Submit and pay

    Most offices take applications online. Expedited review is the norm for home chargers, and some issue the permit the same or the next business day.

  5. Install the charger

    On a circuit sized at 125 percent of the charger's continuous load, with the maker's instructions kept on site for the inspector.

  6. Pass the inspection

    Someone has to be there to give access to the panel and charger. Don't use the charger until the permit is finaled.

What changes from city to city

How you apply
Most offices take applications online, but Vista still wants them in person at the counter, Solana Beach and National City take them by email, and Coronado accepts email, mail or a visit.
Whether a house needs drawings
The City of San Diego, Chula Vista and San Marcos need no plan set for a single-family home. Encinitas and Solana Beach want plans stamped or signed by a C-10 contractor or electrical engineer, and El Cajon wants a scaled site plan plus a single-line diagram for chargers of 50 amps or more.
How long it takes
The County issues home charger permits the same day, Carlsbad the next business day after payment, and Encinitas and San Marcos aim for 1 to 3 business days.
How inspections are booked
Escondido takes requests only through its portal, Lemon Grove by voicemail before 3 p.m., and Coronado by phone before 4 p.m. Imperial Beach and National City don't inspect on Fridays.

What offices usually ask for

When an office doesn't publish its own list, these are the items the others ask for most:

  • The office's permit application, with the contractor's license number
  • A load calculation, often on the office's own circuit card or worksheet
  • The charger maker's specifications and installation instructions
  • A site plan showing the panel, the charger and the route between them
  • A single-line diagram, usually only for larger chargers or new subpanels

What state law requires

Since AB 1236 (2015), every California city and county has had to offer an expedited, administrative permit for EV chargers, limited to a health and safety review, with its checklist posted online and electronic signatures accepted. An incomplete application gets one notice listing everything that's missing.

AB 970 (2021) added deadlines. For a project of 1 to 25 chargers, an application is deemed complete if the office doesn't respond within 5 business days, and deemed approved if it then takes no action within 20 business days, unless it finds a specific health or safety problem.

Sources: GO-Biz: AB 970 process timelines; GO-Biz: AB 1236 and AB 970.

Frequently asked questions

Do I need a permit for a home EV charger in San Diego County?

For a Level 2 charger, yes. It runs on a 240-volt circuit, and every permit office we checked treats that as permitted, inspected work. A Level 1 charger plugged into an existing 120-volt outlet usually needs no permit; Escondido and Solana Beach say so in their guidance, though adding a new outlet does need one.

How long does an EV charger permit take?

It depends on the office: same day in unincorporated areas, the next business day after payment in Carlsbad, and a goal of 1 to 3 business days in Encinitas and San Marcos. Under state law (AB 970), an application for 1 to 25 chargers is deemed complete if the office doesn't respond within 5 business days, and deemed approved if it then takes no action within 20 business days, unless it finds a specific health or safety problem.

Can a homeowner pull the permit?

Sometimes. The City of San Diego has an owner-builder form, DS-3042, for owners doing their own work. The County requires the installation to be done by a certified, licensed electrician, and Encinitas and Solana Beach want plans stamped or signed by a C-10 contractor or electrical engineer.

Ready to charge at home?

Send a photo of your panel and where the car parks. We quote a fixed price and carry out the installation ourselves.

Get a free quote

Prefer to talk? Call (619) 202-8501.

Get quote