How to permit a home EV charger in Encinitas

Encinitas uses its BLD-119 checklist for every EV charger. Submittals are online only, through the Customer Self Service portal, and expedited applications have a review goal of 1 to 3 business days.

Checked against the office's own website on October 12, 2026.

Encinitas at a glance

Permit office
City of Encinitas Development Services
How to apply
Online only, Customer Self Service (CSS) portal
What a house submits
Short digital plan set, stamped by a C-10 contractor or electrical engineer
Turnaround
1 to 3 business days (expedited goal)
Inspection
Booked in the CSS portal

Step by step in Encinitas

  1. Register for a CSS account

    All Encinitas submittals are electronic, through the Customer Self Service portal.

  2. Prepare the plan set

    A title page, the charger maker's installation details and specifications, and electrical service load calculations, stamped and signed by a C-10 contractor or a California electrical engineer. Size the branch circuit at 125 percent of the charger's continuous load.

  3. Add what the location requires

    A site plan isn't required for a Level 2 charger inside an existing one- or two-family house or garage. If the charger is in a residential building, show the smoke and carbon monoxide alarm locations.

  4. Submit the application and BLD-119

    Upload the building permit application, the plan set and the completed checklist. Explain any checklist item you can't meet.

  5. Review

    The Building Department reviews it; Planning, Engineering and Fire usually don't. Expedited applications have a processing goal of 1 to 3 business days.

  6. Install and inspect

    Schedule the inspection in the CSS portal, give the inspector the approved plans and access, and get final approval before using the charger.

What can change the process in Encinitas

Battery storage

Fire review comes in only if the system includes a stationary storage battery.

Questions: (760) 633-2730 or building@encinitasca.gov.

Let us handle the permit

Our C-10 licensed, in-house team files the permit, books the inspection and meets the inspector, and the permit is part of the fixed price. Read about EV charger installation in Encinitas or Tesla Wall Connector installation in Encinitas.

Get a free quote

Sources: City of Encinitas checklist BLD-119. Rules and fees change; the office's own pages have the final word.