How to permit a home EV charger in Encinitas
Encinitas uses its BLD-119 checklist for every EV charger. Submittals are online only, through the Customer Self Service portal, and expedited applications have a review goal of 1 to 3 business days.
Checked against the office's own website on October 12, 2026.
Encinitas at a glance
- Permit office
- City of Encinitas Development Services
- How to apply
- Online only, Customer Self Service (CSS) portal
- What a house submits
- Short digital plan set, stamped by a C-10 contractor or electrical engineer
- Turnaround
- 1 to 3 business days (expedited goal)
- Inspection
- Booked in the CSS portal
Step by step in Encinitas
Register for a CSS account
All Encinitas submittals are electronic, through the Customer Self Service portal.
Prepare the plan set
A title page, the charger maker's installation details and specifications, and electrical service load calculations, stamped and signed by a C-10 contractor or a California electrical engineer. Size the branch circuit at 125 percent of the charger's continuous load.
Add what the location requires
A site plan isn't required for a Level 2 charger inside an existing one- or two-family house or garage. If the charger is in a residential building, show the smoke and carbon monoxide alarm locations.
Submit the application and BLD-119
Upload the building permit application, the plan set and the completed checklist. Explain any checklist item you can't meet.
Review
The Building Department reviews it; Planning, Engineering and Fire usually don't. Expedited applications have a processing goal of 1 to 3 business days.
Install and inspect
Schedule the inspection in the CSS portal, give the inspector the approved plans and access, and get final approval before using the charger.
What can change the process in Encinitas
Battery storage
Fire review comes in only if the system includes a stationary storage battery.
Questions: (760) 633-2730 or building@encinitasca.gov.
Let us handle the permit
Our C-10 licensed, in-house team files the permit, books the inspection and meets the inspector, and the permit is part of the fixed price. Read about EV charger installation in Encinitas or Tesla Wall Connector installation in Encinitas.
Sources: City of Encinitas checklist BLD-119. Rules and fees change; the office's own pages have the final word.